Notice: Function wp_enqueue_script was called incorrectly. Scripts and styles should not be registered or enqueued until the wp_enqueue_scripts, admin_enqueue_scripts, or login_enqueue_scripts hooks. This notice was triggered by the fontawesome handle. Please see Debugging in WordPress for more information. (This message was added in version 3.3.0.) in /home/r1ico/public_html/wp-includes/functions.php on line 6031
M62 Ellentrees | Route One
Warning: Trying to access array offset on value of type null in /home/r1ico/public_html/wp-content/themes/route-one/functions.php on line 647

Warning: Trying to access array offset on value of type null in /home/r1ico/public_html/wp-content/themes/route-one/functions.php on line 654

Case Study

Route One beats programme by four shifts.

Case Study Case Study

M62 Ellentrees

Client: A One+ Area 12

Location: Yorkshire and the Humber

Products: NJ40 Seal, Sentinel Nosing Mortar, Metaset Structural Adhesive, Aluminium Drainage, Safetrack HW, PAR 1 Primer, Rodding Boxes

As part of the current Surfacing and Bridge Joint works in Area 12, Route One completed the Ellentrees section, reducing the programme dramatically by four shifts.

As well as installing the NJ40 Nosing Joint, Route One installed Rodding Boxes to specification to allow for the cleaning of the hydraulic pressure relief drainage.

Rob Thomas, Operations Manager says: “The early successful completion of this key project was a joint collaborative effort between Route One and Area 12. Well done everyone!”

  • Partnership with A One+ Supply Chain
  • Rodding Boxes designed and produced to A One+ specification
  • NJ40 Nosing Joint installed
  • Reduced programme by four shifts