Notice: Function wp_enqueue_script was called incorrectly. Scripts and styles should not be registered or enqueued until the wp_enqueue_scripts, admin_enqueue_scripts, or login_enqueue_scripts hooks. This notice was triggered by the fontawesome handle. Please see Debugging in WordPress for more information. (This message was added in version 3.3.0.) in /home/r1ico/public_html/wp-includes/functions.php on line 6031
A34 Wolvercote Viaduct, Oxford | Route One
Warning: Trying to access array offset on value of type null in /home/r1ico/public_html/wp-content/themes/route-one/functions.php on line 647

Warning: Trying to access array offset on value of type null in /home/r1ico/public_html/wp-content/themes/route-one/functions.php on line 654

A34 Wolvercote Viaduct, Oxford

Case Study Case Study

A34 Wolvercote Viaduct, Oxford

Client: National Highways

Location: South East

As part of our ongoing works for the National Highways Area 3 Contract, Route One Infrastructure was the Principal Contractor for the full deck refurbishment of the A34 Wolvercote structure. The A34 Wolvercote viaduct carries a dual carriageway across a river, a railway line and the A40 in Oxfordshire.

The project, which was to extend the life of the structure, was planned to take 6 weekend closures to complete, however Route One was able to complete in just four weeks, to the delight of the customer and the travelling public.

Our operatives worked around the clock from Friday evening through to Monday morning each weekend to minimise disruption and Route One had to coordinate not just our own works but other contractors to ensure all works were completed in the agreed weekend closures provided.

This was one of many projects for National Highways the team has completed in the South of England, working to the highest of standards to limit any interruptions to the general public.